Jacuzzi Room Update
J Room update I will be moving the jacuzzi tomorrow morning first thing. Patio doors will also be fitted.
J Room update I will be moving the jacuzzi tomorrow morning first thing. Patio doors will also be fitted.
Extension roof will go on tomorrow and will be rendered and painted this week. Fountain under construction
The Latest photos of the garden and swimming pool The garden has been cleared up and we have washed down the stone walls. I have ordered you some new picon. Pump House and filter are in place with a concrete plinth for the heat pump. I have used an old beam I had for the
Pool update and BBQ area. I will put in a wall light and plug sockets either side of the BBQ also the worktop height will allow for you to put in an under counter (beer) fridge if needed.
The block work is now finished with the exception of possibly raising the BBQ wall, these photos should give you an idea of the finished wall heights, I think we have managed to give some privacy without loosing the views. View from top patio View from bottom patio View from bottom patio when pretending to
Surrounding wall is one meter high i have built curved steps to the top patio area as it matches the curved roof above.
The backfill is now in and we have vibrated the soil with a compactor, then laid down a steel mesh with steel reinforcing bars with the screed on top. The picture below has the man pointing out the shower drain to the left of the gate way. I think 4 blocks high around the pool
The walls for the terrace are now in, tomorrow is a fiesta so will backfill on Thursday, then it will start to look like a pool. The block work is seperated every few meters with a reinforced column for added strength this is also connected to the foundations
Hi Ron, Here are some up to date pictures of the pool. Water was delivered on Monday so work is cracking on again. Water pump is fine. The steel has been put in the pool base and the copper wire for the earth has been soldered to it with two one metre copper spikes driven
We finished pouring the swimming pool base last Thursday and have now started the block work which is now at the half way stage. I have had to pull the men off the job for a few days as we have just been hit by a sirocco (hot winds from Africa) The temp reaches 110