Hitesh

Playa Blanca – The foundations

By |2008-04-19T04:59:35+00:00April 19th, 2008|Current Projects, Hitesh|

The steel work is nearly complete and ready for the concrete to be poured on Monday morning. I have had site meeting with the surveyor (aparejador) Mª­ Angeles Pazos Agüera, (she also works for the Arrecife council) on Friday morning we went through the plans and was happy with the changes we made. The technical

Preparing the site

By |2008-04-10T19:16:04+00:00April 10th, 2008|Hitesh|

We have installed the electrical boxes ready for Unelco to supply electricity for the site. We have completed the excavation on both plots of land for the aljibe (water tank) and the waste tank. All tools and machinery have been delivered to the site and we will start on the foundations tomorrow. Click on photos