Carpentry Now Installed
The doors have now been fitted and architraves on the frames. Shower floors are finished and we are waiting for the glass walls to be delivered tomorrow. Floor tiles are grouted and the skirting tiles are done.
The doors have now been fitted and architraves on the frames. Shower floors are finished and we are waiting for the glass walls to be delivered tomorrow. Floor tiles are grouted and the skirting tiles are done.
The lower level garden areas are now finished and the top coat of back-fill is used to cover the water tanks and waste pipes. The shuttering has been placed to help protect the stone walls from any falling rocks. We have installed the electrics for the jacuzzis and the water pipes for the pool shower
The final structural part of the project are the swimming pools. We have leveled the base and compacted the soil ready for a thin layer of concrete. This gives us a base to work on. A steel mesh is constructed of 12mm steel on top of which we pour approx 20cm thick concrete. The base
The second villa has now been rendered and had its first coat of paint. The block work for the stairs and balconies has bean completed and ready for rendering and we are currently shuttering up the top of the plastic membrane to keep the damp out of the basement. The plasterers have started
The stairs on villa one have been shuttered and poured so we now have access to the basement through the rear of the villa. The external stairway that connects the swimming pool area to the lower garden area is also finished. The rendering on villa one is finished and we have
The villas are now ready for the external rendering and the internal plastering to begin. We have finished building the internal walls and fitted the timber pre-frames for the internal doors. The roofs have been rendered and water proofed with a fine fiberglass mesh and rubber paint, We have started to
Natura Design -Lanzarote Builders We have started to build the internal walls for the second villa and our electrician is installing the plastic conduits, plug and switch sockets for the electrics to be run through at the final stage of building, when the villas are nearly completed. The plumbing has been installed for
On the first new villa construction we have built the parapets and screeded the roof, allowing sufficient fall for the water to drain away. This is a time consuming process but must be done correctly to ensure that there are no future problems concerning drainage and leaky roofs. It is also very important to finish
All the acro props have been removed bar a few and we have started to chop out the walls for the electrical conduits. The Lounge The Kitchen The View from the Kitchen into the sitting room. The view from the lounge into the Kitchen.
Both Villas are now roofed , the final blocks are being placed on the roof of the second villa and we will be ready for pouring the concrete in the next couple of days.