The stairs on villa one have been shuttered and poured so we now have access to the basement through the rear of the villa.

    

The external stairway that connects the swimming pool area to the lower garden area is also finished.

    

The rendering on villa one is finished and we have given it one coat of paint for protection.

    

Villa 2 – On the secand villa we are building the internal walls, installing the elctrical conduet and fitting the door and window frames ready for rendering and plastering.