The concrete lorry and concrete pump have arrived to start the first section of wall for the basement. We have started with a twenty six metre section of shuttering. The panels are painted with a product to stop them sticking to the cement. The site has been inspected by Applus the technical control company for the seguro decenal and the quality control have taken the concrete samples they need.

We have now removed the shuttering ready for the next section of wall.

The block work and steel are now finished for the second villa. The concrete will be poured early next week next after the electrician has soldered the copper wire for the earth.