Lanzarote builders Playa Blanca Update

By |2008-05-20T18:06:30+00:00May 20th, 2008|Current Projects, Hitesh|

Today we are pouring the final concrete for the completion of the basement walls for the second villa. We will also pour all the supporting columns for the first storey. The technical control and quality control technicians visited the site this morning and gave us the ok to pour the concrete. We have started to

Playa blanca build starts to take shape

By |2008-05-11T16:34:54+00:00May 11th, 2008|Current Projects, Hitesh|

Things are starting to take shape. We have finished the foundations on the second villa. The concrete has been poured, levelled and then vibrated to take out any air bubbles. 60 cubic metres of concrete have gone into the foundations, 8 lorry loads. The last section of the basement walls have been poured along with

Playa Blanca construction update

By |2008-05-04T09:45:23+00:00May 4th, 2008|Current Projects, Hitesh|

The concrete lorry and concrete pump have arrived to start the first section of wall for the basement. We have started with a twenty six metre section of shuttering. The panels are painted with a product to stop them sticking to the cement. The site has been inspected by Applus the technical control company for

Pouring the Foundations

By |2008-04-27T10:35:57+00:00April 27th, 2008|Hitesh|

Checking the steel for the foundations before we pour the concrete The concrete lorry and pump arrive and we start pouring, the concrete is also vibrated to remove any air bubbles. The foundations are finished for the first villa, the blocks are rendered then sealed to prevent damp. We fill in between the foundations with

Playa Blanca – The foundations

By |2008-04-19T04:59:35+00:00April 19th, 2008|Current Projects, Hitesh|

The steel work is nearly complete and ready for the concrete to be poured on Monday morning. I have had site meeting with the surveyor (aparejador) Mª­ Angeles Pazos Agüera, (she also works for the Arrecife council) on Friday morning we went through the plans and was happy with the changes we made. The technical

Preparing the site

By |2008-04-10T19:16:04+00:00April 10th, 2008|Hitesh|

We have installed the electrical boxes ready for Unelco to supply electricity for the site. We have completed the excavation on both plots of land for the aljibe (water tank) and the waste tank. All tools and machinery have been delivered to the site and we will start on the foundations tomorrow. Click on photos