Preparing the floor levels ready for the concrete.
The shuttering is in place for the balcony floor off the master bedroom and we are putting in the floor levels ready for the concrete.
The shuttering is in place for the balcony floor off the master bedroom and we are putting in the floor levels ready for the concrete.
We have now finished all the rendering of the front walls for both villas in Playa Blanca.
In this method of plastering a special plaster is used, it has been designed to set quickly after being sprayed on, it is called Yeso Projeccion or Yeso Rapido. When plastering by hand a slow setting plaster must be used, this is called Yeso Lento. A thin top coat of a very fine plaster must
A vital part of owning a swimming pool is that of its cleaning. It is a commitment you undertake when installing your pool whether you take the responsibility on yourself or hire one of the many professional pool maintenance businesses available. You have to ensure that your pool is always clean and safe for your
Good heating system in warm climate Lanzarote is the fourth largest island in the Canaries, which is an archipelago situated just off the north west coast of Africa. In respect to its close proximity to the continent, Lanzarote experiences warm mild weather throughout the year. Indeed, during the summer months temperatures will often soar above
The plastering is now finished in the first villa. This has brightened it up and you can get the feel of what the villa will look like finished. We have nearly finished the damp proofing and are ready to start rendering the front walls leading down to the basements. Natura Design S.L.
The second villa has now been rendered and had its first coat of paint. The block work for the stairs and balconies has bean completed and ready for rendering and we are currently shuttering up the top of the plastic membrane to keep the damp out of the basement. The plasterers have started
We are now clearing the site with the digger and bringing in back fill to raise the ground levels around the villas and bring up the levels for the swimming pools. The rendering is nearly finished for the second villa and we are raising the block-work walls leading to the basement.
The stairs on villa one have been shuttered and poured so we now have access to the basement through the rear of the villa. The external stairway that connects the swimming pool area to the lower garden area is also finished. The rendering on villa one is finished and we have
The villas are now ready for the external rendering and the internal plastering to begin. We have finished building the internal walls and fitted the timber pre-frames for the internal doors. The roofs have been rendered and water proofed with a fine fiberglass mesh and rubber paint, We have started to